OCEANAGOLD (Philippines), Inc. said the operational life of the Didipio gold and copper mine in Northern Luzon has been extended to 2037 following an updated mineOCEANAGOLD (Philippines), Inc. said the operational life of the Didipio gold and copper mine in Northern Luzon has been extended to 2037 following an updated mine

OceanaGold extends Didipio mine life to 2037

2026/03/31 00:02
2분 읽기
이 콘텐츠에 대한 의견이나 우려 사항이 있으시면 crypto.news@mexc.com으로 연락주시기 바랍니다

OCEANAGOLD (Philippines), Inc. said the operational life of the Didipio gold and copper mine in Northern Luzon has been extended to 2037 following an updated mine plan based on recent exploration results.

In a disclosure on Monday, the listed miner said updated mineral resource estimates indicate that Didipio’s open-pit stockpiles will be exhausted by 2032, with a smaller portion of residual ore expected to support operations until 2037.

The company had previously projected the mine’s operations to end in 2035, based on its 2023 technical report.

The Didipio mine operates under a Financial or Technical Assistance Agreement with the government, under which the state receives 60% of net revenue while the company receives 40%.

OceanaGold said the Didipio mine has a combined measured and indicated ore volume of 45.2 million metric tons (MT) as of Dec. 31, including 32 MT from underground operations and 13.2 MT from open-pit stockpiles.

Measured and indicated gold resources totaled 1.34 million ounces (Moz), consisting of 1.21 Moz from underground operations and 0.12 Moz from open-pit stockpiles.

Silver resources were estimated at 2.4 Moz, while copper resources were placed at 0.16 MT.

Proved and probable reserves for the combined underground and open-pit stockpiles include 1.13 Moz of gold, 2.2 Moz of silver, and 0.13 MT of copper.

The company said the updated resource estimates provide a basis for medium- to long-term mine planning.

“While ongoing monthly, quarterly and annual reconciliation fluctuations are expected, the Mineral Resource estimates are believed to provide an acceptable basis for medium to long-term mine planning purposes,” it said.

OceanaGold said it plans to increase processing throughput to 4.3 MT per annum, the current permitted limit, by 2027.

To support the extended mine life and higher underground production, the company said it is upgrading its mining infrastructure.

“Upgrades are underway to existing infrastructure to support increased underground mining rates, including primary ventilation upgrades to support mining at depth and increased fleet requirements,” the company said.

OceanaGold said it is also improving its surface paste plant and underground reticulation network, and investing in dewatering and electrical infrastructure upgrades. — Vonn Andrei E. Villamiel

시장 기회
Based 로고
Based 가격(BASED)
$0.13259
$0.13259$0.13259
+9.92%
USD
Based (BASED) 실시간 가격 차트
면책 조항: 본 사이트에 재게시된 글들은 공개 플랫폼에서 가져온 것으로 정보 제공 목적으로만 제공됩니다. 이는 반드시 MEXC의 견해를 반영하는 것은 아닙니다. 모든 권리는 원저자에게 있습니다. 제3자의 권리를 침해하는 콘텐츠가 있다고 판단될 경우, crypto.news@mexc.com으로 연락하여 삭제 요청을 해주시기 바랍니다. MEXC는 콘텐츠의 정확성, 완전성 또는 시의적절성에 대해 어떠한 보증도 하지 않으며, 제공된 정보에 기반하여 취해진 어떠한 조치에 대해서도 책임을 지지 않습니다. 본 콘텐츠는 금융, 법률 또는 기타 전문적인 조언을 구성하지 않으며, MEXC의 추천이나 보증으로 간주되어서는 안 됩니다.

Roll the Dice & Win Up to 1 BTC

Roll the Dice & Win Up to 1 BTCRoll the Dice & Win Up to 1 BTC

Invite friends & share 500,000 USDT!